nerdexam
PMIPMI

PMP · Question #1265

PMP Question #1265: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1265. The question stem and answer options stay visible for context.

Submitted by luis.pe· Apr 18, 2026Process

Question

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion. What should the project manager do?

Options

  • ARaise a change request to the change control board (CCB) and inform the project sponsor about
  • BUpdate the project management plan and adjust the project budget with this change request.
  • CAsk the key stakeholder to take the lead in handling the request since they are more
  • DRequest a meeting with the stakeholders and their team members to inform them about this

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Integrated Change Control#Stakeholder Management#Project Governance
Full PMP PracticeBrowse All PMP Questions