nerdexam
PMIPMI

PMP · Question #1255

PMP Question #1255: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1255. The question stem and answer options stay visible for context.

Submitted by jian89· Apr 18, 2026Process

Question

A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs) reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees. Which document should the project manager update first to document this change?

Options

  • ASchedule baseline
  • BScope baseline
  • CRisk register
  • DCost baseline

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Risk Register#Integrated Change Control#Risk Response Planning
Full PMP PracticeBrowse All PMP Questions