A project manager is leading a project at a contracting company, and the project team just completed an iteration. The product passed inspection, but an additional feature was added to the product…
The correct answer is A. Follow the proper change control process and evaluate the change for further impact. To prevent unauthorized features from being added to a product in an agile environment and causing customer concern, the project manager must enforce a proper change control process to evaluate all changes.
Question
Options
- AFollow the proper change control process and evaluate the change for further impact.
- BPerform frequent reviews with the customer to ensure that the product is working as expected.
- CManage the scope baseline to influence the factors that drive change.
- DWork with the customer to ensure the feature adds value.
How the community answered
(43 responses)- A72% (31)
- B16% (7)
- C5% (2)
- D7% (3)
Why each option
To prevent unauthorized features from being added to a product in an agile environment and causing customer concern, the project manager must enforce a proper change control process to evaluate all changes.
Following the proper change control process is essential to prevent unauthorized additions and ensure that any proposed new features are formally reviewed, approved, and evaluated for potential impacts and risks before implementation. This ensures all changes align with customer expectations and project objectives, avoiding unexpected issues.
Working with the customer to ensure the feature adds value is a reactive measure after an unauthorized feature has already been introduced and caused concern, rather than a proactive measure to avoid the situation in the future.
Concept tested: Change control in agile projects, scope management
Source: https://www.pmi.org/pmbok-guide-standards/agile/agile-practice-guide