PMI
PMP · Question #1234
PMP Question #1234: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1234. The question stem and answer options stay visible for context.
Submitted by lars.no· Apr 18, 2026Process
Question
During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the required IT system. What should the project manager do?
Options
- AFast track this dependency to avoid delaying the project.
- BPerform Integrated Change Control.
- CAsk IT to prioritize the needed system to meet the schedule.
- DInclude the dependency in the project schedule.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Project Scheduling#Dependency Management#Activity Sequencing#Project Planning