PMIPMI
PMP · Question #1218
PMP Question #1218: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1218. The question stem and answer options stay visible for context.
Submitted by paula_co· Apr 18, 2026Process
Question
A new relevant project stakeholder suggested a change to some of the project parameters midway through execution. What should the project manager do next?
Options
- AReject the change because it is contrary to what was agreed to during earlier phases of the
- BTransfer the change to the steering committee for them to evaluate and decide the appropriate
- CEvaluate the proposed change with integrated change controls and discuss the change with the
- DAccept the change and use contingency funds to implement this change with minimal schedule
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Integrated Change Control#Stakeholder Engagement#Change Request Process