PMIPMI
PMP · Question #1200
PMP Question #1200: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1200. The question stem and answer options stay visible for context.
Submitted by neha2k· Apr 18, 2026Process
Question
A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event. What should the project manager do first?
Options
- AUse the contingency fund.
- BUpdate the risk register.
- CPrepare a change request.
- DFollow the risk response plan.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Risk Response Plan#Risk Monitoring & Control#Critical Path