Question
In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope. What should the project manager do?
Options
- ARaise this issue, and review and update the progress report for the next monthly project meeting.
- BCommunicate with an officer in the environmental protection department to check if it is
- COrganize a meeting with the team and update the work breakdown structure (WBS).
- DStart the organization's change control process via a change request.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Integrated Change Control#Scope Management#Change Request#Project Governance