PMP · Question #1186
PMP Question #1186: Real Exam Question with Answer & Explanation
The correct answer is A: Requested an experienced resource as a replacement. To avoid project delays when a critical resource departs, the project manager should proactively request an experienced replacement capable of quickly assuming the role and responsibilities.
Question
An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month. What should the project manager have done to avoid this scenario?
Options
- ARequested an experienced resource as a replacement
- BNegotiated additional time to complete the project
- CAllocated additional time for mentoring
- DConvinced the critical resource to remain on the project
Explanation
To avoid project delays when a critical resource departs, the project manager should proactively request an experienced replacement capable of quickly assuming the role and responsibilities.
Common mistakes.
- B. Negotiating additional time is a reactive measure after a problem has occurred, rather than a proactive step to prevent the initial delay caused by an inexperienced replacement.
- C. While mentoring is beneficial, allocating additional time for mentoring an intern in a critical role during a critical phase only prolongs the impact and doesn't solve the immediate skill gap for critical tasks.
- D. Convincing a critical resource to remain is often not within a project manager's direct control, especially if the resource has already made a decision to leave.
Concept tested. Resource management and critical role replacement
Topics
Community Discussion
No community discussion yet for this question.