nerdexam
PMI

PMP · Question #1186

An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months lat

Sign in or unlock PMP to reveal the answer and full explanation for question #1186. The question stem and answer options stay visible for context.

Submitted by wei.xz· Apr 18, 2026Process

Question

An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month. What should the project manager have done to avoid this scenario?

Options

  • ARequested an experienced resource as a replacement
  • BNegotiated additional time to complete the project
  • CAllocated additional time for mentoring
  • DConvinced the critical resource to remain on the project

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Staffing#Risk Mitigation#Schedule Management
Full PMP Practice