nerdexam
PMI

PMP · Question #118

A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office (PMO) recommends the project manager to lead the next simil

Sign in or unlock PMP to reveal the answer and full explanation for question #118. The question stem and answer options stay visible for context.

Submitted by yaw92· Apr 18, 2026Process

Question

A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office (PMO) recommends the project manager to lead the next similar project. What should the project manager do next?

Options

  • AEngage key stakeholders to complete and deliver lessons learned.
  • BSelect the same stakeholders for the next project to avoid doing knowledge transfer.
  • CPresent the project achievements and delegate knowledge transfer to the steering committee.
  • DRequest the PMO to manage the lessons learned repository.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Lessons Learned#Project Closure#Organizational Process Assets#Stakeholder Engagement
Full PMP Practice