PMP · Question #1109

PMP Question #1109: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1109. The question stem and answer options stay visible for context.

Submitted by dimitri_ru· Apr 18, 2026Process

Question

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable. What should the project manager have done to avoid this situation?

Options

  • AEnsured the project repository is up to date.
  • BMade an effort to reemploy the senior project team member.
  • CUpdated the job descriptions for all team roles.
  • DProvided specialist training for all team members.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Knowledge Management#Information Management#Team Resilience#Risk Management