nerdexam
PMIPMI

PMP · Question #1104

PMP Question #1104: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1104. The question stem and answer options stay visible for context.

Submitted by ravi_2018· Apr 18, 2026Process

Question

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

Options

  • AUpdate the stakeholder register.
  • BConsult the project sponsor.
  • CRefer to the resource management plan.
  • DModify the statement of work (SOW).

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Resource Planning#Risk Response#Contingency Planning
Full PMP PracticeBrowse All PMP Questions