nerdexam
PMIPMI

PMP · Question #1089

PMP Question #1089: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1089. The question stem and answer options stay visible for context.

Submitted by tom_us· Apr 18, 2026Process

Question

In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

Options

  • AEmpower the team members to do their work.
  • BWork with the team to develop a risk response plan.
  • CSend an email to human resources (HR) about this situation.
  • DInform the project sponsor about this situation.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk management#Schedule delays#Problem-solving#Team collaboration
Full PMP PracticeBrowse All PMP Questions