PMIPMI
PMP · Question #1085
PMP Question #1085: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1085. The question stem and answer options stay visible for context.
Submitted by lucia.co· Apr 18, 2026Process
Question
During project execution, a client asks to add one more features to the product. After performing a change request analysis, the project manager realizes the necessary equipment will not be available in time to support this new feature, resulting in the project team being idle. What should the project manager do next?
Options
- AEstablish a contingency reserve.
- BRent ready-made equipment.
- CEscalate the risk to senior management.
- DPerform integrated change control.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Integrated Change Control#Project Execution