nerdexam
PMIPMI

PMP · Question #1067

PMP Question #1067: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1067. The question stem and answer options stay visible for context.

Submitted by cyberguy42· Apr 18, 2026Process

Question

A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project's required inputs. The project manager planned a reserve budget to allow the project to continue in the event of this occurrence. What should the project manager do?

Options

  • ATell the project team to stop work, as software support will be canceled and the project cannot
  • BAdvise the supplier that the sponsor will pay for software support as previously planned.
  • CAsk the supplier to continue providing software support until the end of the project.
  • DInform the sponsor that the risk has been realized and that a decision has to be made for the

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Stakeholder Communication#Risk Response Implementation#Issue Management
Full PMP PracticeBrowse All PMP Questions