PMIPMI
PMP · Question #1062
PMP Question #1062: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1062. The question stem and answer options stay visible for context.
Submitted by obi.ng· Apr 18, 2026Process
Question
A few key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, the project schedule is seriously delayed. What should the project manager do?
Options
- ARequest additional resources to be incorporated to the project team.
- BObserve the project team and give them time to catch up before escalating.
- CEscalate to the project sponsor and seek alternatives to resolve the issue.
- DReview the issues and adjust the project plan to give a realistic schedule.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Escalation#Issue Management#Stakeholder Communication#Schedule Management