nerdexam
PMIPMI

PMP · Question #1060

PMP Question #1060: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1060. The question stem and answer options stay visible for context.

Submitted by tarun92· Apr 18, 2026Process

Question

A project that has to be delivered by the targeted date has been delayed due to an unforeseen risk occurrence. How should the project manager compress the project to ensure the completion date is not affected?

Options

  • AAdd more project resources
  • BFast-track the project
  • CReduce the project scope
  • DIncrease the project cost

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Schedule Management#Schedule Compression#Fast-tracking
Full PMP PracticeBrowse All PMP Questions