nerdexam
PMIPMI

PMP · Question #1033

PMP Question #1033: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1033. The question stem and answer options stay visible for context.

Submitted by hassan_iq· Apr 18, 2026Process

Question

Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months. What should the project manager do?

Options

  • AShift those key members and assign them to another project.
  • BCancel the meeting series until the marketing team provides a solution.
  • CConsult the project team and discuss the key team members' availability.
  • DConsult the resource management plan and escalate to the sponsor.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Issue Resolution#Sponsor Engagement#Stakeholder Management
Full PMP PracticeBrowse All PMP Questions