PMP · Question #1031
A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new…
The correct answer is C. Perform an impact analysis on the schedule and budget based on the additional scope. When a new capability is requested mid-project, the project manager's immediate next step is to assess the impact on the project's schedule and budget before committing to the change.
Question
Options
- ARevise the project schedule and budget based on the additional scope, and review with the team.
- BInclude the new capability to the product backlog and continue activities based on the current
- CPerform an impact analysis on the schedule and budget based on the additional scope.
- DAnalyze and negotiate with the executive steering committee regarding this new request.
How the community answered
(33 responses)- A3% (1)
- B6% (2)
- C79% (26)
- D12% (4)
Why each option
When a new capability is requested mid-project, the project manager's immediate next step is to assess the impact on the project's schedule and budget before committing to the change.
Revising the schedule and budget immediately without first performing an impact analysis is premature, as the full extent of the change is not yet understood.
Simply adding the new capability to the product backlog and continuing without assessing the impact on the current sprint or overall project ignores the immediate disruption and potential resource conflicts.
Before revising the project plan or negotiating, a project manager must first understand the implications of the requested change. Performing an impact analysis on the schedule and budget provides the necessary data to determine feasibility, potential trade-offs, and inform subsequent discussions with stakeholders.
Negotiating without first understanding the impact of the change would put the project manager at a disadvantage, as they would lack the data to make a strong case or propose alternatives.
Concept tested: Scope change management and impact analysis
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/control-scope-process
Topics
Community Discussion
No community discussion yet for this question.