nerdexam
PMIPMI

PMP · Question #1031

PMP Question #1031: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1031. The question stem and answer options stay visible for context.

Submitted by ahmad_uae· Apr 18, 2026Process

Question

A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability to perform a what-if analysis in the tool based on the customer demand and forecast. What should the project manager do next?

Options

  • ARevise the project schedule and budget based on the additional scope, and review with the team.
  • BInclude the new capability to the product backlog and continue activities based on the current
  • CPerform an impact analysis on the schedule and budget based on the additional scope.
  • DAnalyze and negotiate with the executive steering committee regarding this new request.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Scope Management#Change Control#Impact Analysis#Stakeholder Management
Full PMP PracticeBrowse All PMP Questions