PMP · Question #102
PMP Question #102: Real Exam Question with Answer & Explanation
The correct answer is D: Update the issue log and act to minimize the impact. A critical supplier bankruptcy has become an issue impacting the project schedule, so the project manager must first document it as an issue and then address its impact.
Question
During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule. What should the project manager do first?
Options
- AEscalate to the management team for delay approval
- BAdd the risk and the delay to the risk register
- CUpdate the schedule to include the delay
- DUpdate the issue log and act to minimize the impact
Explanation
A critical supplier bankruptcy has become an issue impacting the project schedule, so the project manager must first document it as an issue and then address its impact.
Common mistakes.
- A. Escalating for delay approval is premature; the project manager first needs to understand the full impact and potential solutions before seeking approval for a delay.
- B. This is no longer a risk; it's an actual event, so it should be managed as an issue, not added to the risk register.
- C. Updating the schedule is an action that follows the identification and initial assessment of the issue; the immediate first step is to recognize and log the issue and plan a response.
Concept tested. Issue management in project execution
Topics
Community Discussion
No community discussion yet for this question.