nerdexam
PMIPMI

PMP · Question #102

PMP Question #102: Real Exam Question with Answer & Explanation

The correct answer is D: Update the issue log and act to minimize the impact. A critical supplier bankruptcy has become an issue impacting the project schedule, so the project manager must first document it as an issue and then address its impact.

Submitted by andres_qro· Apr 18, 2026Process

Question

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule. What should the project manager do first?

Options

  • AEscalate to the management team for delay approval
  • BAdd the risk and the delay to the risk register
  • CUpdate the schedule to include the delay
  • DUpdate the issue log and act to minimize the impact

Explanation

A critical supplier bankruptcy has become an issue impacting the project schedule, so the project manager must first document it as an issue and then address its impact.

Common mistakes.

  • A. Escalating for delay approval is premature; the project manager first needs to understand the full impact and potential solutions before seeking approval for a delay.
  • B. This is no longer a risk; it's an actual event, so it should be managed as an issue, not added to the risk register.
  • C. Updating the schedule is an action that follows the identification and initial assessment of the issue; the immediate first step is to recognize and log the issue and plan a response.

Concept tested. Issue management in project execution

Topics

#Issue Management#Risk Realization#Corrective Action#Project Monitoring and Control

Community Discussion

No community discussion yet for this question.

Full PMP PracticeBrowse All PMP Questions