PMI-ACP · Question #755

PMI-ACP Question #755: Real Exam Question with Answer & Explanation

The correct answer is B: Balance risk reduction and value adding activities in the next iteration.. In agile, risk management is balanced against delivering value. When a severe risk is discovered, the right response is to incorporate risk reduction work into the next iteration alongside value-adding activities, rather than abandoning the current sprint mid-stream. Option A is

Submitted by tunde_lagos· Apr 18, 2026Adaptive Planning

Question

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

Options

  • AAdd a goal to the current iteration to fully mitigate or control the risk.
  • BBalance risk reduction and value adding activities in the next iteration.
  • CContinue with the current plan to maintain team velocity.
  • DUpdate the risk register and seek direction from a risk specialist.

Explanation

In agile, risk management is balanced against delivering value. When a severe risk is discovered, the right response is to incorporate risk reduction work into the next iteration alongside value-adding activities, rather than abandoning the current sprint mid-stream. Option A is wrong because adding a goal to the current iteration disrupts the sprint commitment and team focus. Option C is wrong because ignoring a severe risk to maintain velocity is irresponsible and contrary to agile principles. Option D is partially useful (updating the risk register is good practice) but deferring entirely to a risk specialist removes team ownership of risk management, which is not aligned with agile values.

Topics

#Agile Risk Management#Adaptive Planning#Iteration Planning#Prioritization