An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?
The correct answer is B. Balance risk reduction and value adding activities in the next iteration. In agile, risk management is balanced against delivering value. When a severe risk is discovered, the right response is to incorporate risk reduction work into the next iteration alongside value-adding activities, rather than abandoning the current sprint mid-stream. Option A…
Question
An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?
Options
- AAdd a goal to the current iteration to fully mitigate or control the risk.
- BBalance risk reduction and value adding activities in the next iteration.
- CContinue with the current plan to maintain team velocity.
- DUpdate the risk register and seek direction from a risk specialist.
How the community answered
(24 responses)- A4% (1)
- B83% (20)
- C4% (1)
- D8% (2)
Explanation
In agile, risk management is balanced against delivering value. When a severe risk is discovered, the right response is to incorporate risk reduction work into the next iteration alongside value-adding activities, rather than abandoning the current sprint mid-stream. Option A is wrong because adding a goal to the current iteration disrupts the sprint commitment and team focus. Option C is wrong because ignoring a severe risk to maintain velocity is irresponsible and contrary to agile principles. Option D is partially useful (updating the risk register is good practice) but deferring entirely to a risk specialist removes team ownership of risk management, which is not aligned with agile values.