The correct answer is B: Balance risk reduction and value adding activities in the next iteration.. In agile, risk management is balanced against delivering value. When a severe risk is discovered, the right response is to incorporate risk reduction work into the next iteration alongside value-adding activities, rather than abandoning the current sprint mid-stream. Option A is
Question
An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?
Options
- AAdd a goal to the current iteration to fully mitigate or control the risk.
- BBalance risk reduction and value adding activities in the next iteration.
- CContinue with the current plan to maintain team velocity.
- DUpdate the risk register and seek direction from a risk specialist.
Explanation
In agile, risk management is balanced against delivering value. When a severe risk is discovered, the right response is to incorporate risk reduction work into the next iteration alongside value-adding activities, rather than abandoning the current sprint mid-stream. Option A is wrong because adding a goal to the current iteration disrupts the sprint commitment and team focus. Option C is wrong because ignoring a severe risk to maintain velocity is irresponsible and contrary to agile principles. Option D is partially useful (updating the risk register is good practice) but deferring entirely to a risk specialist removes team ownership of risk management, which is not aligned with agile values.