nerdexam
PMIPMI

PMI-ACP · Question #732

PMI-ACP Question #732: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #732. The question stem and answer options stay visible for context.

Submitted by renata2k· Apr 18, 2026Problem Detection and Resolution

Question

During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay. What should the scrum master advise the team to do?

Options

  • AImplement the story since the team is running behind schedule.
  • BCreate a spike to finalize the story's technical approach.
  • CTransfer the story to a scrum team experienced in solving similar problems.
  • DAsk the product owner to reduce the story's priority and wait until more technical details are

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Spikes#Technical impediments#Scrum Master role#Problem-solving
Full PMI-ACP PracticeBrowse All PMI-ACP Questions