Submitted by renata2k· Apr 18, 2026Problem Detection and Resolution
Question
During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay. What should the scrum master advise the team to do?
Options
- AImplement the story since the team is running behind schedule.
- BCreate a spike to finalize the story's technical approach.
- CTransfer the story to a scrum team experienced in solving similar problems.
- DAsk the product owner to reduce the story's priority and wait until more technical details are