PMI-ACP · Question #732
During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay. What should the scrum master advise the team to do?
The correct answer is B. Create a spike to finalize the story's technical approach. A spike is a time-boxed agile research task specifically designed to resolve technical uncertainty. When a story's technical approach is unclear or problematic, creating a spike allows the team to investigate, prototype, and determine the correct path before committing to full…
Question
During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay. What should the scrum master advise the team to do?
Options
- AImplement the story since the team is running behind schedule.
- BCreate a spike to finalize the story's technical approach.
- CTransfer the story to a scrum team experienced in solving similar problems.
- DAsk the product owner to reduce the story's priority and wait until more technical details are
How the community answered
(14 responses)- A7% (1)
- B71% (10)
- C7% (1)
- D14% (2)
Explanation
A spike is a time-boxed agile research task specifically designed to resolve technical uncertainty. When a story's technical approach is unclear or problematic, creating a spike allows the team to investigate, prototype, and determine the correct path before committing to full implementation. Option A (implement anyway) ignores the technical challenge and risks building the wrong solution. Option C (transfer to another team) is disruptive and not the standard response. Option D (reduce priority and wait) delays value delivery unnecessarily when a bounded investigation (spike) can resolve the uncertainty.
Topics
Community Discussion
No community discussion yet for this question.