PMI-ACP · Question #622

An agile team notices that the same problems continue to occur during multiple iterations. Several team members have suggestions to fix the problem. What is the proper agile approach to handle this?

The correct answer is A. Hold frequent retrospectives and share the responsibility for making changes. Retrospectives are the core agile mechanism for continuous process improvement. When recurring problems surface, the team collectively inspects their process and adapts - this is a foundational agile principle. Sharing responsibility means no single person owns the fix; the…

Submitted by salim_om· Apr 18, 2026Continuous Improvement

Question

An agile team notices that the same problems continue to occur during multiple iterations. Several team members have suggestions to fix the problem. What is the proper agile approach to handle this?

Options

  • AHold frequent retrospectives and share the responsibility for making changes
  • BUnderstand that this is the nature of innovative business and strive to work harder
  • CCollect team member feedback and discuss them privately with the product owner
  • DConduct a team-building exercise to increase trust among the team members

How the community answered

(42 responses)
  • A
    86% (36)
  • B
    5% (2)
  • C
    7% (3)
  • D
    2% (1)

Explanation

Retrospectives are the core agile mechanism for continuous process improvement. When recurring problems surface, the team collectively inspects their process and adapts - this is a foundational agile principle. Sharing responsibility means no single person owns the fix; the whole team commits to improvement actions. Option B (work harder) ignores root cause analysis. Option C (discuss privately with the product owner) bypasses team ownership and transparency. Option D (team-building exercises) addresses trust but not the specific operational problems causing repeated failures.

Topics

#Retrospectives#Continuous Improvement#Problem Solving#Team Collaboration

Community Discussion

No community discussion yet for this question.