The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business. What…

The correct answer is A. Demonstrated only the completed stories and seek stakeholder feedback. If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.

Submitted by kavita_s· Apr 18, 2026Value-driven Delivery

Question

The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business. What should the product owner have done differently?

Options

  • ADemonstrated only the completed stories and seek stakeholder feedback
  • BPresented the budget situation and review the cost variance
  • CReviewed the test results to gain confidence from the stakeholders
  • DPresented a demo of all the stories including the work in progress stories

How the community answered

(55 responses)
  • A
    80% (44)
  • B
    7% (4)
  • C
    2% (1)
  • D
    11% (6)

Explanation

If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.

Topics

#Iteration Review#Product Owner Role#Stakeholder Feedback#Increment Demonstration