PMI-ACP · Question #564
The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business. What…
The correct answer is A. Demonstrated only the completed stories and seek stakeholder feedback. If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.
Question
The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business. What should the product owner have done differently?
Options
- ADemonstrated only the completed stories and seek stakeholder feedback
- BPresented the budget situation and review the cost variance
- CReviewed the test results to gain confidence from the stakeholders
- DPresented a demo of all the stories including the work in progress stories
How the community answered
(55 responses)- A80% (44)
- B7% (4)
- C2% (1)
- D11% (6)
Explanation
If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.