Kanban cards should always be written using User Stories.

The correct answer is B. False. Kanban is a flow management method that is format-agnostic regarding work items. A Kanban card can represent any unit of work: a bug fix, a support ticket, a maintenance task, an administrative action, or a user story. Unlike Scrum, which prescribes user stories as a primary…

Submitted by andres_qro· Apr 18, 2026Adaptive Planning

Question

Kanban cards should always be written using User Stories.

Options

  • ATrue
  • BFalse

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    95% (20)

Explanation

Kanban is a flow management method that is format-agnostic regarding work items. A Kanban card can represent any unit of work: a bug fix, a support ticket, a maintenance task, an administrative action, or a user story. Unlike Scrum, which prescribes user stories as a primary backlog format, Kanban imposes no such requirement. The card simply needs to represent a discrete, trackable piece of work appropriate to the team's context.

Topics

#Kanban#Kanban cards#User Stories#Work items

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice