PMI-ACP · Question #530
PMI-ACP Question #530: Real Exam Question with Answer & Explanation
The correct answer is E: Throughput. Throughput is the primary measure of productivity in Kanban, defined as the number of work items (or story points) completed per unit of time (e.g., per week). It directly reflects how much value the team is delivering. Cycle time measures how long an individual item takes to com
Question
The measure of productivity of a Kanban team is:
Options
- ACycle time
- BLead Time
- CWork in Progress
- DVelocity
- EThroughput
Explanation
Throughput is the primary measure of productivity in Kanban, defined as the number of work items (or story points) completed per unit of time (e.g., per week). It directly reflects how much value the team is delivering. Cycle time measures how long an individual item takes to complete, lead time measures from request to delivery, WIP is a constraint metric, and velocity is a Scrum-specific measure — none of these serve as the overarching productivity metric in Kanban the way throughput does.
Topics
Community Discussion
No community discussion yet for this question.