nerdexam
PMI

PMI-ACP · Question #530

The measure of productivity of a Kanban team is:

The correct answer is E. Throughput. Throughput is the primary measure of productivity in Kanban, defined as the number of work items (or story points) completed per unit of time (e.g., per week). It directly reflects how much value the team is delivering. Cycle time measures how long an individual item takes to…

Submitted by hassan_iq· Apr 18, 2026Team Performance

Question

The measure of productivity of a Kanban team is:

Options

  • ACycle time
  • BLead Time
  • CWork in Progress
  • DVelocity
  • EThroughput

How the community answered

(36 responses)
  • A
    3% (1)
  • C
    3% (1)
  • E
    94% (34)

Explanation

Throughput is the primary measure of productivity in Kanban, defined as the number of work items (or story points) completed per unit of time (e.g., per week). It directly reflects how much value the team is delivering. Cycle time measures how long an individual item takes to complete, lead time measures from request to delivery, WIP is a constraint metric, and velocity is a Scrum-specific measure - none of these serve as the overarching productivity metric in Kanban the way throughput does.

Topics

#Kanban Metrics#Throughput#Productivity Measurement#Team Performance

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice