nerdexam
PMIPMI

PMI-ACP · Question #513

PMI-ACP Question #513: Real Exam Question with Answer & Explanation

The correct answer is C: A risk of not creating a potentially shippable product occurs. In Scrum, each Sprint should produce a 'Done' Increment — a potentially releasable product. Testing is typically part of the Definition of Done. If testing is incomplete, the Increment may not meet the Definition of Done, which means the product may not be in a shippable state.

Submitted by haruto_sh· Apr 18, 2026Value-driven Delivery

Question

What happens if all the necessary testing doesn't occur in a Sprint?

Options

  • AThe User Story is moved to the next Sprint
  • BAdditional testers are added in the next Sprint
  • CA risk of not creating a potentially shippable product occurs
  • DThe Burndown chart is updated

Explanation

In Scrum, each Sprint should produce a 'Done' Increment — a potentially releasable product. Testing is typically part of the Definition of Done. If testing is incomplete, the Increment may not meet the Definition of Done, which means the product may not be in a shippable state. This creates delivery risk. Stories are not simply moved to the next Sprint as a routine practice, and adding testers or updating burndown charts do not address the core problem. The team should prevent this by ensuring the Definition of Done is realistic and achievable within the Sprint.

Topics

#Definition of Done#Potentially Shippable Increment#Sprint Goal#Testing Quality

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions