nerdexam
PMIPMI

PMI-ACP · Question #512

PMI-ACP Question #512: Real Exam Question with Answer & Explanation

The correct answer is C: The Product Owner. The Scrum Guide explicitly states: 'The Product Owner is responsible for maximizing the value of the product resulting from the work of the Development Team.' This includes managing and ordering the Product Backlog. While the Development Team and stakeholders provide input, the P

Submitted by saadiq_pk· Apr 18, 2026Value-driven Delivery

Question

Who is responsible for maximizing the value of the product backlog?

Options

  • AThe Customer
  • BThe Scrum Master and Product Owner
  • CThe Product Owner
  • DThe Development Team and Product Owner

Explanation

The Scrum Guide explicitly states: 'The Product Owner is responsible for maximizing the value of the product resulting from the work of the Development Team.' This includes managing and ordering the Product Backlog. While the Development Team and stakeholders provide input, the Product Owner has sole accountability for backlog decisions. The Scrum Master does not share this responsibility — the Scrum Master serves the Product Owner by facilitating Scrum events and helping with backlog management techniques.

Topics

#Product Owner#Product Backlog#Role Responsibilities#Value Maximization

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions