PMI-ACP Question #512: Real Exam Question with Answer & Explanation
The correct answer is C: The Product Owner. The Scrum Guide explicitly states: 'The Product Owner is responsible for maximizing the value of the product resulting from the work of the Development Team.' This includes managing and ordering the Product Backlog. While the Development Team and stakeholders provide input, the P
Question
Who is responsible for maximizing the value of the product backlog?
Options
- AThe Customer
- BThe Scrum Master and Product Owner
- CThe Product Owner
- DThe Development Team and Product Owner
Explanation
The Scrum Guide explicitly states: 'The Product Owner is responsible for maximizing the value of the product resulting from the work of the Development Team.' This includes managing and ordering the Product Backlog. While the Development Team and stakeholders provide input, the Product Owner has sole accountability for backlog decisions. The Scrum Master does not share this responsibility — the Scrum Master serves the Product Owner by facilitating Scrum events and helping with backlog management techniques.
Topics
Community Discussion
No community discussion yet for this question.