nerdexam
PMI

PMI-ACP · Question #429

What Agile concept expresses delivering value in slices rather than in layers/stages?

The correct answer is C. Sashimi. Sashimi is an Agile concept borrowed from the Japanese dish where each slice of fish is complete and ready to eat on its own. In software development, it means each feature or story should be a thin, vertical slice that is fully functional end-to-end (UI through database), rather

Submitted by rachelw· Apr 18, 2026Value-driven Delivery

Question

What Agile concept expresses delivering value in slices rather than in layers/stages?

Options

  • ADefinition of Done
  • BValue Mapping
  • CSashimi
  • DLean Value

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    6% (1)
  • C
    75% (12)
  • D
    13% (2)

Explanation

Sashimi is an Agile concept borrowed from the Japanese dish where each slice of fish is complete and ready to eat on its own. In software development, it means each feature or story should be a thin, vertical slice that is fully functional end-to-end (UI through database), rather than building horizontal layers (e.g., completing all database work, then all logic, then all UI). This contrasts with a 'layer cake' approach. Definition of Done defines completion criteria; Value Mapping and Lean Value are different concepts.

Topics

#Agile Delivery#Vertical Slicing#Incremental Development#Feature Slicing

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice