PMI-ACP · Question #425
PMI-ACP Question #425: Real Exam Question with Answer & Explanation
The correct answer is A: Burndown chart. A burndown chart plots remaining work (story points or tasks) on the Y-axis against time (days in the iteration) on the X-axis. As work is completed each day, the line burns down toward zero. This gives the entire team and stakeholders immediate visual transparency into whether t
Question
At completion of iteration planning, the team has finished identifying the tasks they will commit to for the next iteration. Which of the following tools best provides transparency into the progress throughout the iteration?
Options
- ABurndown chart
- BGantt chart
- CHours expended chart
- DManagement baseline chart
Explanation
A burndown chart plots remaining work (story points or tasks) on the Y-axis against time (days in the iteration) on the X-axis. As work is completed each day, the line burns down toward zero. This gives the entire team and stakeholders immediate visual transparency into whether the team is on track to complete their commitment by the end of the iteration. Gantt charts are plan-oriented and not updated daily; hours-expended and management baseline charts are not standard Agile transparency tools.
Topics
Community Discussion
No community discussion yet for this question.