PMI-ACP · Question #424

What of the following is not a step in the Value Stream Mapping process?

The correct answer is C. Amplify Learning. Value Stream Mapping (VSM) is a Lean technique with four core steps: (1) Define the current state, (2) Collect data, (3) Depict the future state, and (4) Develop an implementation plan. 'Amplify Learning' is NOT a VSM step - it is one of the seven principles of Lean Software…

Submitted by olafpl· Apr 18, 2026Value-driven Delivery

Question

What of the following is not a step in the Value Stream Mapping process?

Options

  • ADefine the current state
  • BCollect data
  • CAmplify Learning
  • DDepict the future state
  • EDevelop an implementation plan

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    92% (23)

Explanation

Value Stream Mapping (VSM) is a Lean technique with four core steps: (1) Define the current state, (2) Collect data, (3) Depict the future state, and (4) Develop an implementation plan. 'Amplify Learning' is NOT a VSM step - it is one of the seven principles of Lean Software Development (Poppendieck). It is a common distractor because Lean and VSM are related, but they are distinct concepts.

Topics

#Value Stream Mapping#Lean#Process Improvement#Agile Techniques