The correct answer is A: Reflect at the end of every iteration and identify improvements that will increase the quality. A retrospective is a structured ceremony held at the end of each iteration where the team reflects on their process — what went well, what didn't, and what specific improvements they will commit to in the next iteration. The goal is continuous process improvement (inspect and a

Submitted by lars.no· Apr 18, 2026Continuous Improvement

Question

Retrospectives provide an opportunity for the team to:

Options

  • AReflect at the end of every iteration and identify improvements that will increase the quality
  • BParticipate in a mandatory meeting to share status updates across the team and to ensure
  • CUnderstand from the management if the project is achieving the Scope, Quality, Cost, and
  • DSet goals at the beginning of the iteration and identify requirements that can be delivered in

Explanation

A retrospective is a structured ceremony held at the end of each iteration where the team reflects on their process — what went well, what didn't, and what specific improvements they will commit to in the next iteration. The goal is continuous process improvement (inspect and adapt). Answer B describes a status meeting (more like a daily standup or project review). Answer C describes a management review, not a team retrospective. Answer D describes iteration planning, not a retrospective.