PMIPMI
PMI-ACP · Question #39
PMI-ACP Question #39: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #39. The question stem and answer options stay visible for context.
Submitted by jordan8· Apr 18, 2026Adaptive Planning
Question
The best approach to estimate the work on a project when using story points is to have:
Options
- ATeam members assign estimates by averaging Planning Poker cards.
- BThe most senior team member prepare the estimates.
- CTwo or three senior team members estimate and take the average of their times.
- DThe team work together to agree on estimates in a group setting.
Unlock PMI-ACP to see the answer
You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile Estimation#Story Points#Team Collaboration#Planning Poker