PMI-ACP · Question #356
PMI-ACP Question #356: Real Exam Question with Answer & Explanation
The correct answer is A: Cycle time. Cycle time is the total number of days (elapsed real-world time) required from when a feature is specified until it is delivered to production. It is a key lean and Agile efficiency metric that measures the end-to-end flow of work through the system. Shorter cycle times indicate
Question
The number of days needed between feature specification and production delivery is called:
Options
- ACycle time
- BReal time
- CIdeal time
- DCalendar time
Explanation
Cycle time is the total number of days (elapsed real-world time) required from when a feature is specified until it is delivered to production. It is a key lean and Agile efficiency metric that measures the end-to-end flow of work through the system. Shorter cycle times indicate a more efficient delivery pipeline. It differs from 'ideal time' (effort in focused hours) and is not the same as 'calendar time,' which is a more general term not specific to the feature development lifecycle.
Topics
Community Discussion
No community discussion yet for this question.