PMI-ACP · Question #357

PMI-ACP Question #357: Real Exam Question with Answer & Explanation

The correct answer is A: It is a static artifact. The Definition of Done (DoD) is NOT a static artifact—it is dynamic and should evolve as the team matures and improves its processes. Teams regularly revisit and update their DoD, especially during Retrospectives. The DoD is correctly described as an auditable checklist (not me

Submitted by klara.se· Apr 18, 2026Team Performance

Question

All of the following are attributes of the definition of "Done", EXCEPT:

Options

  • AIt is a static artifact
  • BIt is an audible checklist
  • CIt is a primary reporting mechanism for team members on User Story progress
  • DIt is crucial to a high-performing team

Explanation

The Definition of Done (DoD) is NOT a static artifact—it is dynamic and should evolve as the team matures and improves its processes. Teams regularly revisit and update their DoD, especially during Retrospectives. The DoD is correctly described as an auditable checklist (not merely 'audible'), a primary reporting mechanism for tracking story completion, and crucial to high-performing teams because it ensures shared understanding of quality and completeness. Calling it 'static' contradicts the Agile principle of continuous improvement.

Topics

#Definition of Done#Agile Quality#Team Collaboration#Increment Completion