PMI-ACP · Question #324

PMI-ACP Question #324: Real Exam Question with Answer & Explanation

The correct answer is A: Burndown Chart. A Burndown Chart tracks the amount of work remaining (vertical axis) over time (horizontal axis). As work is completed, the line trends downward toward zero. It is used at the Sprint, release, or product level to visualize progress and predict completion. A Burnup Chart is the in

Submitted by ravi_2018· Apr 18, 2026Value-driven Delivery

Question

The trend of work remaining across time in a Sprint, a release, or a product, with work remaining tracked on the vertical axis and the time periods tracked on the horizontal axis is called a ____________.

Options

  • ABurndown Chart
  • BBurnup Chart
  • CProgress Chart
  • DParking Lot Chart

Explanation

A Burndown Chart tracks the amount of work remaining (vertical axis) over time (horizontal axis). As work is completed, the line trends downward toward zero. It is used at the Sprint, release, or product level to visualize progress and predict completion. A Burnup Chart is the inverse—it shows work completed trending upward toward a total. A Parking Lot Chart is a high-level status tool showing feature/theme completion, not a time-series of remaining work.

Topics

#Burndown Chart#Agile Metrics#Progress Tracking#Sprint Management

Community Discussion

No community discussion yet for this question.