PMI-ACP · Question #323
PMI-ACP Question #323: Real Exam Question with Answer & Explanation
The correct answer is C: Qualitative Risk Analysis. Agile teams use Qualitative Risk Analysis to identify, assess, and prioritize risks based on their probability and impact—typically using tools like a risk matrix or risk-adjusted backlog. Qualitative analysis is fast and suitable for Agile's iterative cadence. A Risk Burndown
Question
Which type of risk analysis does an Agile team use to identify risks on their project?
Options
- ARisk Burndown Chart
- CQualitative Risk Analysis
- DQuantitative Analysis
Explanation
Agile teams use Qualitative Risk Analysis to identify, assess, and prioritize risks based on their probability and impact—typically using tools like a risk matrix or risk-adjusted backlog. Qualitative analysis is fast and suitable for Agile's iterative cadence. A Risk Burndown Chart is a tool for tracking risk over time (monitoring, not initial identification), and Quantitative Analysis (numerical modeling, Monte Carlo simulation) is more common in large or complex traditional projects.
Topics
Community Discussion
No community discussion yet for this question.