PMI-ACP · Question #27
PMI-ACP Question #27: Real Exam Question with Answer & Explanation
The correct answer is D: Burn down charts indicate whether rate of effort changes are due to changes in progress rates or. Option D is the false statement. It claims burn DOWN charts indicate whether effort changes are due to progress rate changes or scope changes — but the opposite is true. Burn DOWN charts combine scope and progress into a single line, making it impossible to separate the two. Th
Question
Which of the following is not true of how burn up charts that also track total scope differ from burn down charts?
Options
- ABurn up charts separate out the rate of progress from the scope fluctuations
- BBurn up charts and burn down charts trend in opposite vertical directions
- CBurn up charts can be converted to cumulative flow diagrams by the addition of WIP
- DBurn down charts indicate whether rate of effort changes are due to changes in progress rates or
Explanation
Option D is the false statement. It claims burn DOWN charts indicate whether effort changes are due to progress rate changes or scope changes — but the opposite is true. Burn DOWN charts combine scope and progress into a single line, making it impossible to separate the two. This is exactly the advantage of burn UP charts: by showing both completed work and total scope as separate lines, they CAN distinguish between a change in delivery pace and a change in scope. Options A, B, and C are all true statements about burn up charts.
Topics
Community Discussion
No community discussion yet for this question.