PMI-ACP · Question #27

PMI-ACP Question #27: Real Exam Question with Answer & Explanation

The correct answer is D: Burn down charts indicate whether rate of effort changes are due to changes in progress rates or. Option D is the false statement. It claims burn DOWN charts indicate whether effort changes are due to progress rate changes or scope changes — but the opposite is true. Burn DOWN charts combine scope and progress into a single line, making it impossible to separate the two. Th

Submitted by marco_it· Apr 18, 2026Value-driven Delivery

Question

Which of the following is not true of how burn up charts that also track total scope differ from burn down charts?

Options

  • ABurn up charts separate out the rate of progress from the scope fluctuations
  • BBurn up charts and burn down charts trend in opposite vertical directions
  • CBurn up charts can be converted to cumulative flow diagrams by the addition of WIP
  • DBurn down charts indicate whether rate of effort changes are due to changes in progress rates or

Explanation

Option D is the false statement. It claims burn DOWN charts indicate whether effort changes are due to progress rate changes or scope changes — but the opposite is true. Burn DOWN charts combine scope and progress into a single line, making it impossible to separate the two. This is exactly the advantage of burn UP charts: by showing both completed work and total scope as separate lines, they CAN distinguish between a change in delivery pace and a change in scope. Options A, B, and C are all true statements about burn up charts.

Topics

#Burn up charts#Burn down charts#Progress tracking#Scope management