PMI-ACP · Question #181
PMI-ACP Question #181: Real Exam Question with Answer & Explanation
The correct answer is A: 1 day. In Agile, a research story (also called a spike) is a time-boxed investigation task used to gather information, explore solutions, or reduce uncertainty. The standard time-box for a research story is 1 day. This constraint prevents teams from spending too much time on analysis an
Question
What is the normal time estimate for a research story?
Options
- A1 day
- B1 hour
- CHalf an hour
- D1 iteration
Explanation
In Agile, a research story (also called a spike) is a time-boxed investigation task used to gather information, explore solutions, or reduce uncertainty. The standard time-box for a research story is 1 day. This constraint prevents teams from spending too much time on analysis and ensures that the spike produces actionable results quickly, keeping the team moving forward without over-investing in exploration.