PMI-ACP · Question #180
When can a plan be changed in Agile Management?
The correct answer is B. When we have learned something new. In Agile Management, a plan can be changed 'When we have learned something new' (B). This reflects one of Agile's core values: responding to change over following a plan. Agile embraces empiricism - as new information emerges (from stakeholder feedback, changing requirements…
Question
When can a plan be changed in Agile Management?
Options
- AAt the end of the Iteration
- BWhen we have learned something new
- CAt the Daily Meeting
- DYou cannot change once the plan is prepared
How the community answered
(15 responses)- A7% (1)
- B93% (14)
Explanation
In Agile Management, a plan can be changed 'When we have learned something new' (B). This reflects one of Agile's core values: responding to change over following a plan. Agile embraces empiricism - as new information emerges (from stakeholder feedback, changing requirements, technical discoveries, or market shifts), the plan is updated to reflect that learning. Option A (end of iteration) is too restrictive. Option C (Daily Meeting) is incorrect as the Daily Standup is for synchronization, not replanning. Option D contradicts Agile principles entirely.
Topics
Community Discussion
No community discussion yet for this question.