nerdexam
PMIPMI

PMI-ACP · Question #180

PMI-ACP Question #180: Real Exam Question with Answer & Explanation

The correct answer is B: When we have learned something new. In Agile Management, a plan can be changed 'When we have learned something new' (B). This reflects one of Agile's core values: responding to change over following a plan. Agile embraces empiricism — as new information emerges (from stakeholder feedback, changing requirements, t

Submitted by hans_de· Apr 18, 2026Adaptive Planning

Question

When can a plan be changed in Agile Management?

Options

  • AAt the end of the Iteration
  • BWhen we have learned something new
  • CAt the Daily Meeting
  • DYou cannot change once the plan is prepared

Explanation

In Agile Management, a plan can be changed 'When we have learned something new' (B). This reflects one of Agile's core values: responding to change over following a plan. Agile embraces empiricism — as new information emerges (from stakeholder feedback, changing requirements, technical discoveries, or market shifts), the plan is updated to reflect that learning. Option A (end of iteration) is too restrictive. Option C (Daily Meeting) is incorrect as the Daily Standup is for synchronization, not replanning. Option D contradicts Agile principles entirely.

Topics

#Adaptive Planning#Agile Principles#Continuous Learning#Flexibility

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions