nerdexam
PMI

PMI-ACP · Question #176

At a Retrospective meeting, a few issues are highlighted by the team. Who is responsible for solving these issues?

The correct answer is D. Team. In Agile/Scrum, the Team (D) is collectively responsible for identifying and resolving issues raised in the Retrospective. The Retrospective is a self-improvement ceremony owned by the team itself. While the Scrum Master (A) facilitates the meeting and may help remove…

Submitted by javi_es· Apr 18, 2026Continuous Improvement

Question

At a Retrospective meeting, a few issues are highlighted by the team. Who is responsible for solving these issues?

Options

  • AThe Scrum Master
  • BProduct Owner
  • CStakeholders
  • DTeam

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    6% (2)
  • D
    88% (30)

Explanation

In Agile/Scrum, the Team (D) is collectively responsible for identifying and resolving issues raised in the Retrospective. The Retrospective is a self-improvement ceremony owned by the team itself. While the Scrum Master (A) facilitates the meeting and may help remove impediments, and the Product Owner (B) may attend, the primary accountability for process improvements lies with the whole team. Stakeholders (C) are generally not involved in internal Retrospectives.

Topics

#Retrospective#Team responsibility#Self-organizing teams#Continuous improvement

Community Discussion

No community discussion yet for this question.