PMI-ACP · Question #154
PMI-ACP Question #154: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #154. The question stem and answer options stay visible for context.
Submitted by haruto_sh· Apr 18, 2026Value-driven Delivery
Question
A ScrumMaster consistently holds Daily Scrums and keeps them to 15 minutes or less. The ScrumMaster brings a list of assigned tasks and checks the status of each task with the relevant team members. The ScrumMaster then assigns new tasks for the day and ends the meeting. Is this an appropriate approach to running Daily Scrums?
Options
- ARisk management
- BSmall releases
- CProject management
- DProject charter
Unlock PMI-ACP to see the answer
You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Daily Scrum#ScrumMaster role#Self-organizing teams#Incremental delivery