PMI-ACP · Question #153

Which answer best describes Wide Band Delphi (e. g. Planning Poker) estimating?

The correct answer is A. Team members provide story estimates individually and discuss their reasoning until a. Wide Band Delphi (including Planning Poker) is a consensus-based estimating technique where team members independently select their estimates, reveal them simultaneously, and then discuss the reasoning behind differing estimates. This process repeats until the team converges on…

Submitted by skyler.x· Apr 18, 2026Adaptive Planning

Question

Which answer best describes Wide Band Delphi (e. g. Planning Poker) estimating?

Options

  • ATeam members provide story estimates individually and discuss their reasoning until a
  • BTeam performance on prior projects is analyzed, and actual hours and durations are used to
  • CTeam members apply relative sizing to each task, and story points are triangulated based on
  • DTeam members assign a realistic and a pessimistic estimate to each story, and points are

How the community answered

(19 responses)
  • A
    95% (18)
  • B
    5% (1)

Explanation

Wide Band Delphi (including Planning Poker) is a consensus-based estimating technique where team members independently select their estimates, reveal them simultaneously, and then discuss the reasoning behind differing estimates. This process repeats until the team converges on a shared estimate. The simultaneous reveal prevents anchoring bias. Option B describes analogous estimating. Option C partially describes relative sizing but not the Delphi discussion/consensus process. Option D describes a variation of three-point (PERT) estimating, not Delphi.

Topics

#Wide Band Delphi#Planning Poker#Agile Estimating#Team Estimation