PMI-ACP · Question #140
PMI-ACP Question #140: Real Exam Question with Answer & Explanation
The correct answer is C: Use velocity of past iterations or make a calculated guess.. The most reliable method for estimating initial velocity is to use historical data from past iterations of similar work, or if none exists, to make a calculated guess based on team size and capacity. Using past velocity accounts for real-world factors like interruptions, dependen
Question
When estimating initial velocity, the team should most likely:
Options
- ADiscuss among the team their expectations of how many story points they can address.
- BUse a Kanban workflow to identify steps and calculate velocity.
- CUse velocity of past iterations or make a calculated guess.
- DDiscuss with the customer their expectation for the velocity of producing the product.
Explanation
The most reliable method for estimating initial velocity is to use historical data from past iterations of similar work, or if none exists, to make a calculated guess based on team size and capacity. Using past velocity accounts for real-world factors like interruptions, dependencies, and team throughput. Option A (team discussion) is too subjective and optimistic. Option B (Kanban) is a different methodology. Option D (customer expectations) is inappropriate — velocity is a team metric, not a customer deliverable.