The correct answer is B: Product roadmap. A product roadmap is a strategic, high-level view that maps out which features or themes are planned for future releases over time. It differs from a release plan (A), which is more tactical and sprint-level, and an iteration plan (C), which covers a single sprint. The Product Ba
Question
What is a high-level representation of the features or themes that are to be delivered in each release?
Options
- ARelease plan
- BProduct roadmap
- CIteration plan
- DProduct Backlog
Explanation
A product roadmap is a strategic, high-level view that maps out which features or themes are planned for future releases over time. It differs from a release plan (A), which is more tactical and sprint-level, and an iteration plan (C), which covers a single sprint. The Product Backlog (D) is a prioritized list of all work items but does not organize them into release timelines. The roadmap communicates direction and vision to stakeholders.
Topics
Community Discussion
No community discussion yet for this question.