You are using the Power BI service to view a visual on a report that has been shared with you. You need to add the visual to a dashboard as a tile. Which action should you perform?

The correct answer is B. Pin. An entire report page can be pinned to a dashboard, which is called pinning a live tile. It's called a live tile because you can interact with the tile on the dashboard. Unlike with individual visualization tiles, changes made in the report are automatically synced with…

Submitted by andreas_gr· Apr 18, 2026Describe the business value of Microsoft Power Platform

Question

You are using the Power BI service to view a visual on a report that has been shared with you. You need to add the visual to a dashboard as a tile. Which action should you perform?

Options

  • AExport data
  • BPin
  • CCopy
  • DSpotlight

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    89% (39)
  • C
    5% (2)
  • D
    2% (1)

Explanation

An entire report page can be pinned to a dashboard, which is called pinning a live tile. It's called a live tile because you can interact with the tile on the dashboard. Unlike with individual visualization tiles, changes made in the report are automatically synced with https://docs.microsoft.com/en-us/power-bi/create-reports/service-dashboard-pin-tile-from-report

Topics