PK0-005 · Question #82
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepa
The correct answer is A. Pareto. A Pareto chart (bar chart ordered by frequency, with a cumulative line) is specifically designed to prioritize quality issues by identifying which defects occur most often - based on the 80/20 principle that roughly 80% of problems stem from 20% of causes. A run chart tracks data
Question
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?
Options
- APareto
- BRun
- CControl
- DHistogram
How the community answered
(66 responses)- A74% (49)
- B14% (9)
- C8% (5)
- D5% (3)
Explanation
A Pareto chart (bar chart ordered by frequency, with a cumulative line) is specifically designed to prioritize quality issues by identifying which defects occur most often - based on the 80/20 principle that roughly 80% of problems stem from 20% of causes. A run chart tracks data over time for trends. A control chart monitors process stability with control limits. A histogram shows distribution of data but does not inherently prioritize causes for action.