PK0-005 · Question #643
A project manager wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following would be the best option for the…
The correct answer is C. PERT chart. A PERT chart (Program Evaluation and Review Technique) is a network diagram that visually maps all project tasks as nodes and shows their dependencies and relationships via connecting arrows. It directly answers 'how tasks relate to each other' by displaying sequencing…
Question
A project manager wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following would be the best option for the project manager to use?
Options
- AMilestone chart
- BGantt chart
- CPERT chart
- DBurndown chart
How the community answered
(27 responses)- A4% (1)
- C96% (26)
Explanation
A PERT chart (Program Evaluation and Review Technique) is a network diagram that visually maps all project tasks as nodes and shows their dependencies and relationships via connecting arrows. It directly answers 'how tasks relate to each other' by displaying sequencing, predecessors, and successors. A milestone chart (A) only shows key dates, not task relationships. A Gantt chart (B) shows tasks against a timeline but does not clearly depict task interdependencies as a network. A burndown chart (D) tracks remaining work over time and has nothing to do with task organization or relationships.
Topics
Community Discussion
No community discussion yet for this question.