nerdexam
CompTIA

PK0-005 · Question #636

The project manager asks the project scheduler to create a PERT chart. Which of the following best describes the reason for this request?

The correct answer is D. To incorporate multiple time estimates for activities. A PERT chart is used to incorporate multiple time estimates for activities, allowing the project manager to account for uncertainty by using optimistic, pessimistic, and most likely duration estimates to better predict project timelines.

Tools and documentation

Question

The project manager asks the project scheduler to create a PERT chart. Which of the following best describes the reason for this request?

Options

  • ATo display contingency activities and associated buffer
  • BTo ensure all project tasks are assigned to a resource
  • CTo provide senior management a shortlist of important dates
  • DTo incorporate multiple time estimates for activities

How the community answered

(57 responses)
  • A
    2% (1)
  • B
    7% (4)
  • C
    5% (3)
  • D
    86% (49)

Explanation

A PERT chart is used to incorporate multiple time estimates for activities, allowing the project manager to account for uncertainty by using optimistic, pessimistic, and most likely duration estimates to better predict project timelines.

Topics

#PERT chart#Project scheduling#Time estimation#Uncertainty management

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice