PK0-005 · Question #636
The project manager asks the project scheduler to create a PERT chart. Which of the following best describes the reason for this request?
The correct answer is D. To incorporate multiple time estimates for activities. A PERT chart is used to incorporate multiple time estimates for activities, allowing the project manager to account for uncertainty by using optimistic, pessimistic, and most likely duration estimates to better predict project timelines.
Question
The project manager asks the project scheduler to create a PERT chart. Which of the following best describes the reason for this request?
Options
- ATo display contingency activities and associated buffer
- BTo ensure all project tasks are assigned to a resource
- CTo provide senior management a shortlist of important dates
- DTo incorporate multiple time estimates for activities
How the community answered
(57 responses)- A2% (1)
- B7% (4)
- C5% (3)
- D86% (49)
Explanation
A PERT chart is used to incorporate multiple time estimates for activities, allowing the project manager to account for uncertainty by using optimistic, pessimistic, and most likely duration estimates to better predict project timelines.