A project team is working on relating the client's needs to test scenarios, test results, and any issues that might arise. Which of the following is the best tool to collect this information?
The correct answer is D. Requirements Traceability Matrix. A Requirements Traceability Matrix (RTM) is a document that maps client requirements to test cases, test results, and related issues, ensuring every requirement is tested and any gaps are tracked. This directly matches the described activity. A Work Breakdown Structure (A)…
Question
A project team is working on relating the client's needs to test scenarios, test results, and any issues that might arise. Which of the following is the best tool to collect this information?
Options
- AWork breakdown structure
- BStatement of work
- CResponsibility assignment matrix
- DRequirements Traceability Matrix
How the community answered
(23 responses)- A9% (2)
- B4% (1)
- D87% (20)
Explanation
A Requirements Traceability Matrix (RTM) is a document that maps client requirements to test cases, test results, and related issues, ensuring every requirement is tested and any gaps are tracked. This directly matches the described activity. A Work Breakdown Structure (A) decomposes project work into deliverables. A Statement of Work (B) defines the work to be performed contractually. A Responsibility Assignment Matrix (C) maps tasks to team members' roles and responsibilities.