The correct answer is D: Gap analysis. A gap analysis compares the project’s required skills and competencies with the current capabilities of the team, allowing the project manager to determine whether the team can accomplish the project or if additional training or resources are needed.

Tools and documentation

Question

The project manager is assessing the project team's skill set. Which of the following tools would help determine if the team is capable of accomplishing a project?

Options

  • ATeam performance assessment
  • BContingency plan
  • CResource breakdown structure
  • DGap analysis

Explanation

A gap analysis compares the project’s required skills and competencies with the current capabilities of the team, allowing the project manager to determine whether the team can accomplish the project or if additional training or resources are needed.

Topics